Lead to Clean Lead to Green

Both the contractors of LWMC mechanicaly wash major roads as follows.

Albayrak

  • No of Roads = 129
  • No of Kilometers =112KM/Day
  • No of Vehicles Used = 14

Ozpak

  • No of Roads =
  • No of Kilometers =
  • No of Vehicles Used =

Mechanical Washing Plan (Night)

 
DAY 1 (Monday)  
Teams Roads Start Point End Point Length (km) No of Sides Total Length (km)  
 
Team-1 Canal Road Ferozpur Road Mall Road 3.51 2 7.02
Total Length (km) 7.02
Team-2 Canal Road Ferozpur Road Mall Road 3.51 2 7.02
Total Length (km) 7.02
Team-3 Canal Road Mall Road Mugal Pura Underpass 3.67 2 7.34
Total Length (km) 7.34
Team-4 Canal Road Mall Road Mugal Pura Underpass 3.67 2 7.34
Total Length (km) 7.34
Team-5 Anarkali Road Jain Mandar Chowk Circular Road 1.78 2 3.56
Total Length (km) 3.56
Total Length Covered (km) 32.28  
DAY 2  
Teams Roads Start Point End Point Length (km) No of Sides Total Length (km)  
Team-1 Mall Road PMG Chowk Club Chowk (Davis Road) 4.15 2 8.3
Total Length (km) 8.3
Team-2 Mall Road PMG Chowk Club Chowk (Davis Road) 4.15 2 8.3
Total Length (km) 8.3
Team-3 Mall Road Club Chowk (Davis Road) Canal Road 1 4 4
Jail Road Canal Road Aiwan-e-Tijarat Road 1.45 2 2.9
Total Length (km) 6.9
Team-4 Jail Road Canal Road Aiwan-e-Tijarat Road 1.45 2 2.9
Jail Road Aiwan-e-Tijarat Road Qartaba Chowk 1.49 4 5.96
Total Length (km) 8.86
Total Length Covered (km) 32.36  
DAY 3  
Teams Roads Start Point End Point Length (km) No of Sides Total Length (km)  
Team-1 Main Boulevard Gulberg Kalma Chowk Jail Road 3.85 2 7.7
Total Length (km) 7.7
Team-2 Main Boulevard Gulberg Kalma Chowk Jail Road 3.85 2 7.7
Total Length (km) 7.7
Team-3 Allama Iqbal Road Canal Road Railway Station 3.27 2 6.54
Railway Station Round About 0.6 1 0.6
Total Length (km) 7.14
Team-4 Circular Road Azadi chowk 2 Moria Pull 2.2 4 8.8
Total Length (km) 8.8
Total Length Covered (km) 31.34
DAY 4  (Thursday)  
Teams Roads Start Point End Point Length (km) No of Sides Total Length (km)  
Team-1 Upper Mall Road Canal Road Mian Mir Bridge 1.21 4 4.84
Zafar Ali Road Canal Road Jail Road 0.87 4 3.48
Total Length (km) 8.32
Team-2 Jail Road Canal Road Sher Pao Bridge (Railway Lines) 1.94 4 7.76
Total Length (km) 7.76
Team-3 Noor Jahan Road Qaddafi Stadium Roundabout Hussain Chowk 1.1 4 4.4
Liberty Market Liberty Market 0.47 2 0.94
MM Alam Road Ali Zaib Road Hussain Chowk 0.52 4 2.08
Total Length (km) 7.42
Team-4 MM Alam Road Hussain Chowk Main Boulevard Gulberg 1.93 2 3.86
Gulberg Main Market Main Market 0.52 2 1.04
Hali Road Qaddafi Stadium Roundabout Gulberg Main Market 1.52 2 3.04
Total Length (km) 7.94
Total Length Covered (km) 31.44  
DAY 5  
Teams Roads Start Point End Point Length (km) No of Sides Total Length (km)  
Team-1 Ali Zaib Road Center Point Gurmanget Road 2 4 8
Total Length (km) 8
Team 2 Gurmanget Road Jinnah Flyover College Road 2.48 2 4.96
Mehmood Ali Kasori Road Hussain Chowk Gurmanget Road 0.69 2 1.38
Ghalib Road MM Alam Road Main Boulevard Gulberg 0.76 2 1.52
Total Length (km) 7.86
Team-3 Davis Road Mall Road Shimla Pahari 1.28 2 2.56
Egerton Road Shimla Pahari Holiday Inn 0.5 4 2
Holiday Inn Mall Road 0.7 2 1.4
Aiwan-e-Iqbal Road Mall Road Holiday Inn 0.39 2 0.78
Punjab Assembly Road Mall Road Cooper Road 0.46 2 0.92
Total Length (km) 7.66
Team-4 Shadman Main Boulevard Jail Road Fatima Memorial Hospital (2nd Roundabout 1.2 2 2.4
Aiwan-e-Tijarat Road Jail Road Mall Road 1.5 2 3
Ashiq Hussain Road Shama Chowk Mental Hospital 1.4 2 2.8
Total Length (km) 8.2
Team-5 Anarkali Road Jain Mandar Chowk Circular Road 1.78 2 3.56
Total Length (km) 3.56
Total Length Covered (km) 35.28
DAY 6  
Teams Roads Start Point End Point Length (km) No of Sides Total Length (km)  
Team-1 Metro Bus Track Outside Niazi Interchange Jain Mandar Chowk 5.5 1 5.5
Lytton Road Jain Mandar Chowk Qartaba Chowk 1.41 2 2.82
Total Length (km) 8.32
Team-2 Metro Bus Track Outside Qartaba Chowk Naseer Abad Metro Bus Station 7.36 1 7.36
Total Length (km) 7.36
Team-3 Metro Bus Track Outside Naseer Abad Metro Bus Station Kamaha-Lidher Road 7.9 1 7.9
Total Length (km) 7.9
Team-4 Ferozpur Road Kamaha-Lidher Road Kacha Kahna Road 8 1 8
Total Length (km) 8
Team-5 New Azadi Chowk Interchange Main CarriageWay (MCW), Loops & Ramps 2.47 4 9.88
Total Length (km) 9.88
Total Length Covered (km) 41.46  
Day 7  
Teams Road Name Start Point End Point Length of 1 Side (meters) No of Sides Total Length (meters)  
Team-1 Ghari Shahu Flyover(Shalimar Road) Allama Iqbal Road Cooperative Store Chowk 1.304 2 2.608
GT Road Cooperative Store Chk Shalimar Link Road 3.25 2 6.5
Total Length (K-meters) 9.108
Team-2 Lake Road Chuburji Jain Mandar Chowk 0.566 4 2.264
Bank Road Crust Road Istanbul Chowk 0.672 2 1.344
Library Road Nabha Road Mall Road 0.35 2 0.7
Queen's Road Chairing Cross Qartaba Chowk 1.6 2 3.2
Total Length (K-meters) 7.508
Team-3 GT Road Shalimar Link Road Cooperative Store Chk 3.25 2 6.5
Ghari Shahu Flyover(Shalimar Road) Cooperative Store Chowk Allama Iqbal Road 1.304 2 2.608
Total Length (K-meters) 9.108
Team-4 GT Road Shalimar Link Road Quaid-e-Azam Interchange 5.02 2 10.04
Total Length (K-meters) 10.04
Total Length Covered (Km) 35.764
   Over all Total Length Covered (Km) 239.924  
       
               

Mechanically Washing 112km/Day

Mechanical Washing (M/s. Albayrak)